THS Constructors completed the 47,900 SF expansion to the existing 146,000 SF manufacturing facility for Kloeckner Metals.

The expanded building encompasses the existing rail spur for shipping & receiving goods and materials. The building is a pre-engineered steel structure that is supported on caisson foundations. The project also featured a 40 ton crane, high-speed rolling doors, and an internal truck loading dock. Project was completed in 10 months. All work was completed in the facility while operations were ongoing. 

A 45,000 SF addition to the Huger, SC location was completed in 2022. Construction activities included sitework, pile driving, concrete, structural steel, pre-engineered insulated metal building structure, mechanical and electrical.

Delivery Method

Design-Build

Construction Details

Expansion of existing 146,000 metal building, featuring five overhead doors, and rail spur that passes through the structure

Architect

Architectural Design Center, Inc.

Project Duration

10 Months

Engineers

Arrowood & Arrowood, Jennings-Dill, Seamon Whiteside, Walker & Whiteside