Allendale Speculative Building

Location

Allendale, SC

Project Size

50,000 SF

THS was awarded the Allendale Speculative Building project through a traditional design-bid approach.

The one-story facility features a structural steel frame, insulated precast concrete wall panels, and a joisted roof system. Through close collaboration with the design team, THS identified and implemented value engineering opportunities, achieving a 10% reduction in overall construction costs while maintaining project quality and integrity..

Delivery Method

Design-Build

Construction Details

Structural steel frame with insulated precast concrete wall panels

Architect

LS3P

Project Duration

7 Months

Engineers

Alliance Consulting Engineers; PEA of SC; Hensley & Goerling